Time of the essence in construction contracts
The term ‘Time is of the essence’ refers to a contractual position in which, if one of the parties to the contract fails to complete their obligations by a specified date, then the other party can treat the contract as terminated. This might be appropriate for example in the supply of perishable goods where late delivery would go to the ‘root’ of the contract, depriving the innocent party of the whole benefit of the contract. They may then terminate the contract and claim damages.
Time can be of the essence if the contract says it is, or where it can be implied from the contract. Setting a completion date is not sufficient to make time of the essence. However, where one party has caused delay, the other party can give notice requiring completion by a certain date, thereby making time of the essence.
Typically on construction contracts, time is not of the essence, but rather a completion date is set (the date by which practical completion must be certified). There are generally mechanisms allowing the completion date to be adjusted, and liquidated damages can be claimed by the client if delays that are the fault of the contractor result in a failure to complete the works by the completion date. However, the contract is not terminated, and to do so would generally not be in the interests of either party.
If ‘time is at large’, ie there is no date for completion, or the date for completion has become invalid (with no mechanism for extension), then the contractor is no longer bound by the obligation to complete the works by a certain date. The client would then not be able to claim liquidated damages from the contractor and the contractor would only have to complete the works in a 'reasonable' time. The client would then only be entitled to damages if they could established that the contract was not completed within a reasonable time.
Whilst time is generally not of the essence in construction contracts, they do tend to include a requirement that the contractor proceeds ‘regularly and diligently’ irrespective of whether it is apparent that the completion date will be achieved.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, retrofit measures and the roles involved.
New alliance will tackle skills shortage in greater Manchester
The pioneering Electrotechnical Training and Careers Alliance.
Drone data at the edge: three steps to better AI insights
Offering greater accuracy and quicker access to insights.
From fit-out to higher-risk buildings.
Heritage conservation in Calgary
The triple bottom line.
College of West Anglia apprentice wins SkillELECTRIC gold.
Scottish government launch delivery plan
To strengthen planning and tackle the housing emergency.
How people react in ways which tend to restore their comfort.
Comfort is a crucial missing piece of the puzzle.
ECA launches Recharging Electrical Skills Charter in Wales
Best solutions for the industry and electrical skills in Wales.
New homebuilding skills hub launch and industry response
Working with CITB and NHBC to launch fast track training.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.